Schedule of Values
AIA G702/G703 — Schedule of Values
Palm Beach Warehouse Ph.1 · Draw 4 · April 2026
#DescriptionScheduled valuePrev. completedThis periodStoredTotal completed% CompleteBalance
01Site Work & Mobilization$48,000$48,000$0$0$48,000
100%
$0
02Concrete Foundation$88,000$88,000$0$0$88,000
100%
$0
03Structural Steel$124,000$96,000$0$0$96,000
77%
$28,000
04Electrical Rough-In$92,000$55,200$36,800$0$92,000
100%
$0
05Plumbing Rough-In$48,750$9,750$19,500$0$29,250
60%
$19,500
06Drywall & Framing$62,000$31,000$15,500$0$46,500
75%
$15,500
07HVAC Equipment$143,000$57,200$0$0$57,200
40%
$85,800
08Roofing$76,000$0$0$0$0
0%
$76,000
09Finishes & Painting$41,000$0$0$0$0
0%
$41,000
10Sitework & Paving$55,000$0$0$0$0
0%
$55,000
Totals$777,750$385,150$71,800$0$456,95059%$320,800
Retainage (10%): $45,695
Net payment due: $26,105